Posts without a date wait in the Unscheduled column. Drag them onto a day to schedule them.

Updated 1 min read

In short

  1. In the calendar you switch between week and month. With a trackpad, or Shift and the mouse wheel, you turn exactly one week or month.
  2. Unscheduled has two parts: approved posts that only need a date come first (Ready to schedule), your drafts sit folded below.
  3. Drag an approved post onto a day and it is scheduled. A draft dropped on a day only gets its target date and stays a draft.
  4. Double-click an empty day to add a post there.